Vestas receives order for V82-1.65 MW turbines in the USA


Company announcement from                                                       
Vestas Wind Systems A/S                                                         


Randers, 29 June 2007                                                          
Company announcement No. 27/2007                                               

                                                                                
Vestas receives order for V82-1.65 MW turbines in the USA                       

Vestas has received a 68 MW order in the USA consisting of 41 units of the      
V82-1.65 MW turbine. Wisconsin Power and Light Company has placed the order, and
the turbines are to be installed at the Cedar Ridge Wind Farm in the Townships  
of Eden and Empire in Fond du Lac County, Wisconsin. Delivery will begin in the 
first quarter of 2008 and the project is expected to be completed by the end of 
2008. The order includes supply and commissioning of the turbines plus a        
two-year service and maintenance agreement.                                     

Wisconsin Power and Light Company is a subsidiary of Alliant Energy Corporation,
a public utility holding company headquartered in Madison, Wisconsin. Alliant   
Energy serves over 1.4 million utility customers in Iowa, Minnesota and         
Wisconsin, and purchases electricity generated by wind power plants all across  
the upper Midwest. The Cedar Ridge Wind Farm will be Wisconsin Power and Light  
Company's first fully owned-and-operated wind power plant.                      
                                                                                
“We have in the past worked successfully with Alliant Energy, and we are        
extremely pleased that Wisconsin Power and Light Company will be installing our 
V82-1.65 MW turbine at the Cedar Ridge Wind Farm,” says Jens Søby, President of 
Vestas Americas A/S and continues: “The order adds to the other V82-1.65 MW     
projects in the Wisconsin area and once again demonstrates just how suitable    
this turbine is for the prevailing wind conditions in the area.”                

The Cedar Ridge Wind Farm is further evidence of Wisconsin's commitment to clean
and renewable energy. Wisconsin's Renewable Portfolio Standard (RPS) requires   
that Wisconsin Power and Light Company is to get 10 per cent of the electricity 
it supplies from renewable energy sources by 2015. Today, about 4 per cent of   
Wisconsin's electricity consumption is covered by renewables.                   

The above order does not affect Vestas' expectations for 2007 cf. Stock exchange
announcement No. 20/2007 of 15 May 2007.                                        

Any questions may be addressed to Jens Søby, President of Vestas Americas A/S,  
telephone +1 503 327 2000, or to Peter Wenzel Kruse, Vice President of Group    
Communications at Vestas Wind Systems A/S, telephone +45 9730 0000.             

Yours sincerely                                                                 
Vestas Wind Systems A/S                                                         


Ditlev Engel                                                                    
President and CEO