Peab rebuilds a power plant for Vattenfall Peab has been commissioned to rebuild the Akkats power plant in little Lule River north of Jokkmokk. Peab has received the order from Vattenfall and the value of the contract is SEK 164. The commission primarily consists of the land and concrete work involved in rebuilding the power plant from one aggregate to two. The work will commence in August 2008 and is expected to be completed in July 2014. For further information, please contact: Peter Åkerström, Project Manager Peab +46 733 371951 Gösta Sjöström, Information Director Peab +46 733 371010 Peab AB discloses the information provided herein pursuant to the Securities Markets Act and/or the Financial Instruments Trading Act. The information was submitted for publication at 11:00 a.m. on 27 June, 2008. Previous press releases from Peab are available at www.peab.se
Peab rebuilds a power plant for Vattenfall
| Source: Peab AB