Peab has been commissioned to rebuild the Akkats power plant in little Lule
River north of Jokkmokk. Peab has received the order from Vattenfall and the
value of the contract is SEK 164. 

The commission primarily consists of the land and concrete work involved in
rebuilding the power plant from one aggregate to two.
The work will commence in August 2008 and is expected to be completed in  July
2014.

For further information, please contact:
Peter Åkerström, Project Manager Peab +46 733 371951
Gösta Sjöström, Information Director Peab +46 733 371010



Peab AB discloses the information provided herein pursuant to the Securities
Markets Act and/or the Financial Instruments Trading Act. The information was
submitted for publication at 11:00 a.m. on 27 June, 2008.

Previous press releases from Peab are available at www.peab.se