IT – INET Nordic Time Schedule Updated (07/09)


Monday 26 January it was announced that phase 2 of CCP (full solution) will be implemented from and including Friday, 9 October 2009; if needed subject to FSA approval or consent. 

Due to the decision to implement CCP prior to INET, NASDAQ OMX has complied with a request from market participants that INET be postponed. Thus, new launch date for INET is 7 December 2009. The Baltic and Icelandic markets will be migrated on 30 November. 

The INET Nordic web has been updated to reflect these changes. See also presentation INET Nordic – Update on time schedules >>

More material on member test environments and XTP Compatibility solution will be published February 3.

The updated and new documents are listed in the Member web history >>. 

The information is found on http://www.omxnordicexchange.com/memberlogin/INET_Nordic/

The content presented at the INET Nordic member web is subject to discussions and in some cases approval from our FSAs.

Attachments