Progress report on action plan


Reykjavik, 2011-10-03 14:16 CEST (GLOBE NEWSWIRE) -- An agreement between Orkuveita Reykjavikur (OR) and its owners, tackling the company‘s financial situation (The Plan), was announced March 29th 2011. It contains various measures and the Plan’s progress in Q2 2011 is on schedule.

The total progress in the first half of year 2011 is ISK 312 m. over the period’s target figures. The best results are in postponement of investments in utility systems as well as an overall great progress in all areas of the project. Individual reports follow in the table below. It contains total amounts for year 2011 and the progress as of end of Q2 2011.

Influences of external variables are negative during the period and equates to ISK 129 m. Net total of The Plan is therefore ISK 183 m. above target.

 

Agreement The Plan 2011 Actual 1H 2011
Postponement of investments in sewage 0 89.273
Postponement of investments in utility systems 1.205.000 595.616
Decrease in other investments 250,000 121.869
Increase in tariffs 1.122.000 285.239
Reduction in operation costs 300.000 44.791
Sale of assets 1.000.000 123.128
Subordinated loans from owners 8.000.000 7.925.360
Total 11.877.000 9.185.276
Sale of assets previously approved -375.000 -124,875
Total 11.502.000 9.060.401

 All amounts are in ISK ,000