Lysaker, 9 November 2011
NASDAQ OMX Commodities will arrange four Market Wide Acceptance Testing (MWAT) sessions in the period December 15, 2011 – February 9, 2012. The MWATs will be run in the External test 4 -environment that has been used by members and ISVs throughout the Genium INET project.
The MWAT sessions are designed to ensure member and ISV readiness prior to the migration of Commodities to the Genium INET platform. Members are encouraged to participate in all sessions. As a minimum, it is mandatory to participate in at least two MWAT sessions. ISV’s are not required to participate in MWAT sessions unless assigned by their clients. ISVs are expected to support their clients during MWAT.
MWAT Sessions
MWAT Session 1 (15th December 2011)
MWAT Session 2 (19th January 2012)
MWAT Session 3 (26th January 2012)
MWAT Session 4 (9th February 2012)
The following materials are relevant for all members and ISVs participating in MWAT:
- MWAT plan – general information on the arrangements http://nordic.nasdaqomxtrader.com/digitalAssets/76/76689_mwatplan.pdf
- Connectivity document http://nordic.nasdaqomxtrader.com/digitalAssets/76/76440_genium_inet_commodities_connectivity_testoct19_giwt.pdf
- Known Limitations document http://nordic.nasdaqomxtrader.com/digitalAssets/76/76621_knownlimitationsgeniuminetcommodities.pdf
- Daily Schedule http://nordic.nasdaqomxtrader.com/digitalAssets/76/76691_mwatsched.pdf
All of these documents have been placed under the section “Testing/MWAT” on the member extranet.
Further details on the migration time schedule can be found on the member extranet http://nordic.nasdaqomxtrader.com/digitalAssets/76/76137_mtssep2011.pdf
Next steps for members:
- Using the online form, the main migration contact, as appointed by the member in the MWAT registration, should nominate the MWAT sessions you’re organization will participate in. This should be completed by December 1, 2011. http://nordic.nasdaqomxtrader.com/memberextranet/geniuminetforcommodities/premwat/
- Please review the above mentioned documents and those located on the member extranet site to ensure your organizations readiness for MWAT.
- If you have further need for test user IDs to reflect your current production set-up, please order these as soon as possible from memberservices@nasdaqomx.com (Trading, Back Office, FIX/FIX Drop) http://nordic.nasdaqomxtrader.com/memberextranet/geniuminetforcommodities/authorizationuserids/
The member extranet is always updated with the latest Genium INET related documentation.http://nordic.nasdaqomxtrader.com/memberextranet/geniuminetforcommodities (username: omse / password: member)
For technical questions, please contact technicalsupport@nasdaqomx.com
Key Account Management / Trading: desken@nasdaqomx.com
Clearing: co@nasdaqomx.com
Genium INET for Commodities Member Readiness (general questions regarding Genium INET project, registrations to project activities, escalation of project issues): commodities.geniuminet@nasdaqomx.com