SUMMARY OF INTERIM REPORT JANUARY – JUNE 2015


The reporting period was marked by declining gold prices in combination with
lower head grade

The full interim report may be found on the company’s website and is in Swedish
only.

Highlights Q2/2015

  · Gold production was 126.6 kg (195.7), -35%
  · Revenues were 23.1 MSEK (46.1)
  · EBITDA before unrealized losses/gains on derivatives -20,6 MSEK (7.6)
  · Total cash flow was -25.1 MSEK (0,6) after realized gold hedges -11.0 MSEK (
-3.9)
  · Profit after tax was -28.2 MSEK (-0.7)
  · Earnings per share was -0.11 SEK (-0.01)

Highlights H1/2015

  · Gold production 257.9 kg (371.7), -31%
  · Revenues were 54.8 MSEK (83.7)
  · EBITDA before unrealized losses/gains on derivatives was -36.7 MSEK (1.9)
  · Total cash flow was -45.6 MSEK (-12,3) after realized gold hedges -22.0 MSEK
(-7.9)
  · Profit after tax was -60.8 MSEK (-18.1)
  · Earnings per share was -0.23 SEK (-0.14)
  · Investments were 18.9 MSEK (7.1), mainly into exploration
  · Closing cash balance end of June was 67.4 MSEK

Subsequent events

  · New encouraging gold intersections from the Pampalo Deep Extensions
discovered
  · The company started cooperation negotiations with employees in Finland in
order to evaluate the options; continued production or care and maintenance
  · Negotiations on future financing with the Company´s lenders, Nordea and
Finnvera, as well as owners of the gold price hedge have started

Production guidance for 2015

  · The production guidance for 2015 is 550-600 kg of gold.

Key data-Group
                        April - June              January - June
MSEK if not otherwise    2015     2014      +/-     2015     2014      +/-
stated
Revenues                 23.1     46.1    -23.0     54.8     83.7    -28.9
Ebitda before           -20.6      7.6    -28.2    -36.7      1.9    -38.6
unrealised loss on
derivatives
Ebit                    -33.5     -3.4    -30.0    -71.1    -23.6    -47.5
Profit before tax       -34.7     -1.2    -33.5    -74.5    -22.2    -52.3
Net profit              -28.2     -0.7    -27.5    -60.8    -18.1    -42.7
Cash flow               -25.1      0.6    -25.7    -45.6    -12.3    -33.2
Earnings per share      -0.11    -0.01    -0.10    -0.23    -0.14    -0.09
(SEK)

Gold production (kg)    126.6    195.7    -69.2    257.9    371.7   -113.9
Gold production (oz)    4,069    6,292   -2,223    8,290   11,951   -3,661
Milled ore (tonnes)    85,738  104,688  -18,950  161,827  212,554  -50,727

Operations review
The production for the second quarter 2015 amounted to 126.6 kg gold (195.7) at
a cash cost of 1,365 USD/oz (939) while the gold production for the first six
months was 257.9 kg (371.7) at a cash cost of 1,380 USD/oz (1,096).

Key figures by
quarter[1] (http:/
/connect.ne.ci
sion.com#_ftn1)
                      2 014    2 014   2 014   2 014   2 015   2 015
                         Q1       Q2      Q3      Q4      Q1      Q2
Milled ore          107,866  104,688  95,583  87,205  76,089  85,738
(tonnes)
Head grade (Au          2.0      2.3     2.7     2.4     2.1     1.8
gram/tonne)
Gold recovery (%)      81.6     80.3    81.6    82.9    83.8    84.1
Hourly                 94.6     95.7    93.7    89.8    82.8    91.5
utilization (%)
Gold production       176.0    195.7   210.9   179.3   131.3   126.6
(kg)
Gold production       5,659    6,292   6,781   5,765   4,221   4,069
(oz)
LTIFR (12 months         11       16      23      24      25      10
rolling)
Cost per milled          41       39      46      50      59      50
ore tonne (EUR)
Cost per milled         365      349     415     462     577     476
ore tonne (SEK)
Cash Cost             1,271      939     960   1,046   1,394   1,365
(USD/oz) per
quarter
Cash Cost             1,243    1,130   1,127   1,047   1,059   1,154
(USD/oz) rolling
12
months
Gold price            1,293    1,289   1,284   1,229   1,220   1,193
(USD/oz)

Although the access to new stoping areas in the Pampalo underground mine
improved during the quarter, the mining and milling tonnage was still below the
target. The reduced throughput combined with a lower than planned head grade led
to a lower than planned gold production in the quarter. Despite the low head
grade, gold recovery improved during the reporting period.

The hourly utilization rate in the mill was 91.5%, which was a clear improvement
from the previous period and close to the company target.

The production cost per milled tonne of ore amounted to 476 SEK or 50 EUR, which
was also a clear improvement from the previous period. However, the production
unit cost was higher than during the second quarter in the previous year, which
is explained by the temporary decrease of production activities the cost savings
program that was undertaken in 2014 on both personnel and mine development
costs. The higher reported cash cost is mainly due to the lower gold production.

Realised gold hedge
Accumulated paid realized gold hedges since October 2011 amount to 155 MSEK of
which 22 MSEK during the current year.

Health and Safety
The Company’s safety performance during the reporting period improved and was on
a good level. The overall “LTIFR” rate is 10, which is below the industry
average. The Company policy is a safety target of “zero accidents – zero harm”.

Regional exploration
Base of Till sampling program has advanced to Korpi-area and will be followed by
Poiko-area. By June 30 a total of 918 samples have been collected from North
Kuittila, Pampalo, Hosko and Korpi areas. The sampling target for 2015 is 2,000
samples. Assay results are pending.

Diamond core drilling at Korvilansuo was completed during Q2. The drilling
targeted to the possible extensions towards NE and S. In total four diamond
drill holes with a combined length of 487 meters were drilled. Two of the
planned holes had to be cancelled due to weather conditions. Available results
has been reported in Exploration update report – July 3, 2015. Additional assay
results are pending.

Diamond core drilling at Hosko commenced on June 26. The drilling program is
targeting to the depth extension of the high grade zone and to define additional
high grade zones. By June 30 about 220 meters were drilled and 2 holes were
completed of the planned 1,500 meter program. Drilling is in progress and assay
results are pending.

At Rämepuro assay result were received from the drilling program completed in
March 2015. The program consisted of 14 drill holes totalling 1,067 meters and
it was mainly targeted to the area south of the Rämepuro South lens. HA-193
returned an intersection of 1.10m @ 5.3 g/t au. The hole was drilled 50m south
of the Rämepuro South lens

Environment
All operations have been run in accordance with the existing environmental
permits.

Personnel
By the end of the reporting period, the number of personnel was 84 employees.
The contractors working at the Pampalo Gold Mine had 25 employees.

Subsequent events
The Company reported new encouraging gold intersections from the Pampalo Deep
Extensions including holes T-916 7.0m@12.2 g/t gold (incl. 4.0m@20.4 g/t gold)
and T-917 17.0 m@3.2 g/t gold. These holes were drilled to a previously unknown
structure at the Pampalo Deep Northern lens extension and indicate that there
might be previously unknown high-grade lenses at Pampalo.

In addition recently identified new S2-lens extension has been confirmed by the
drill hole number T-910 (6.0m@5.3 g/t gold) at the level 590. The S2-lens has
also been verified with drifting at the upper levels. The most interesting drill
intersections are presented in a separate Exploration Report together with
complete drilling result tables on the Company´s website and in the attachment.

In August, Endomines AB’s fully owned subsidiary Endomines Oy has, in accordance
with Finnish law, invited employee representatives to cooperation negotiations.

The start-up of the negotiations will give the Company the flexibility to
commence temporary or permanent lay-offs should conditions not improve during
the coming months. The cooperation negotiations, relevant to all employees of
Endomines Oy are, under Finnish law, a required first step prior to any
temporary or permanent lay-offs.

During the co-operation negotiations, all alternatives for the Pampalo
operations will be evaluated. These will include putting the mill and the mines
in a care and maintenance mode.

Negotiations with the lender Nordea bank and gold price hedge owners have also
commenced.

Outlook for 2015
The production guidance for 2015 is 550-600 kg gold. The production guidance for
the second half of year 2015 is based on an updated production plan.

Financial Calendar 2015
Full quarterly reports in Swedish as well as a summary report in English will be
released on October 29 (Q3 2015).

For further information, please contact:
Markus Ekberg, CEO of Endomines AB, tel. +358 40 706 48 50

Alternatively, visit the Company´s home page: www.endomines.com

Endomines AB discloses the information provided herein pursuant to the Swedish
Securities Markets Act and/or the Swedish Financial Instruments Trading Act. The
information was submitted for publication at 08:45 CEST on August 13, 2015.

About Endomines:
Endomines conducts exploration and mining business along the 40 kilometer long
Karelian Gold Line. Through various regulatory approvals, Endomines controls the
exploration rights to this entire area.

The Company’s first mine, Pampalo, started in February 2011. During 2014,
Endomines initiated the production of ore from the mine in Rämepuro. All ore is
processed in the centrally located mill at Pampalo.

The Company’s business practices and mining operations are based on sustainable
principles and on minimizing the impact on the environment.

Endomines applies SveMin's & FinnMin's respective rules for reporting for public
mining & exploration companies. The Company has chosen to report mineral
resources and ore reserves according to the JORC-code, which is the
internationally accepted Australasian code for reporting ore reserves and
mineral resources.

Endomines vision is to participate in the future structural transformation and
consolidation of the Nordic mining industry. The Company may therefore be
involved in acquisitions of interesting deposits or companies, should such
opportunities arise.

The shares of Endomines AB are quoted on NASDAQ Stockholm under ticker ENDO and
on NASDAQ Helsinki under ticker ENDOM. The Liquidity Provider in both Stockholm
and Helsinki is Erik Penser Bankaktiebolag.

----------------------------------------------------------------------

[1] Production figures for the last quarter are partly based on company own
assaying and not confirmed by any external laboratory. Figures are individually
rounded off.