UPDATED FEASIBILITY STUDY COMPLETED FOR THE SILVER-MINE


 

* Cash Cost will be 6,6 $/Oz during the first 6 years
* All-In Cash Cost will be 8,7 $/Oz
* Payback: less than 3 years from start of production 
* 36 % IRR, € 50 million NPV (@ 5 %) (calculated with a consensus
  silver-price of $14,9-20,0/Oz Ag)
* LOM CAPEX 40 M€, of which 29,6 M€ is initial investment

 


Sotkamo Silver has updated the Bankable Feasibility Study for the
Company\'s Silver Mine-project in Sotkamo, Finland. The study shows good
profitability, even at silver-prices under current levels. Production is
expected to start late 2017 or early 2018. Calculations are based on new
information of the ore-reserves, ore-sorting, present costs, new
mining-schedule and latest quotes from suppliers, construction- and
entrepreneurial-companies.

According to cash flow forecast, which is based on an average
silver-price of 14,9 - 20 $/Oz between the years 2016-2022, the Mine´s
project IRR is estimated to 36% and NPV to € 50 million (@ 5%). Pay-back
period from production-start is estimated to be less than 3 years.

The Cash Cost was calculated to find the minimum average silver-price
required, to achieve positive cash flow. If the revenues from the
by-products lead, zinc and gold besides silver are used the cash cost
will be 6,6 €/Oz during the first 6 production-years.

At the All in Cash Cost, sustaining investments during production years
are taken into consideration. The All-In Cash Cost is 8,7 $/Oz.

Cash Cost and the annual ore and country rock mining from open pit as
well as underground ore and development mining are presented in figure
below.

 



The Ore Reserves are estimated to be totally 2.76 million tons with an
average silver-content of 124 g/ton. The estimation has been done
according to the Australasian JORC Code (2012). During the third
production-year, feed capacity will be increased from 350,000 to 450,000
tons per annum in conjunction with the updated environmental-permit.

If the silver-price 28 $/Oz is used, the estimated IRR is 85 % and NPV
is 124 million € (@ 5%). With a silver-price of 12,7 $/Oz, the estimated
IRR is 11% and NPV is 9 million € (@ 5%).

The updated study has been prepared, compiled, evaluated and approved by
the independent consultant-group, CTS Engtec Oy.

Jouni Kankkunen MSc (Mining), MAusIMM, has compiled the mining plan and
ore-reserve estimate. Outotec (Finland) Oyj has, carried out a review on
the mine-technology, the Silver Mine’s mine-plan and the mineral-reserve
estimates for the Feasibility Study. This review was performed by Pekka
Loven, MSc (Mining), MAusIMM (CP) at Outotec (Finland) Oyj. He is a
Competent Person under the (JORC, 2012. The updated ore reserves are
based on information from the updated Bankable Feasibility Study and
information from Sotkamo Silver.

The updated financial figures have been prepared, compiled, evaluated
and approved by the independent consulting company, CTS Engtec Oy.

Jouni Kankkunen MSc (Mining), MAusIMM and Ilkka Tuokko, MSc (Geology),
MAusIMM have compiled and reviewed the plans and estimated the figures
for the Management´s view. Ilkka Tuokko is one of the Management team
and he is not an independent consultant.

\"\"This update of the Feasibility study shows that new mining plan and
pre-concentrating with ore sorter have increased amount of silver in the
ore-feed to the mill which increases resistance against periods of low
silver-prices. The results also show that the measures and investments
we have undertaken during recent years have been successful.

The \"Cash Cost\" and \"All-In Cash Cost\" have reduced significantly.
As to this, I look positive towards the nearest future and I am
confident that we will achieve the targets which we have set\", says
Timo Lindborg, CEO.

 

Stockholm 22th March 2016

Sotkamo Silver AB (publ)

Timo Lindborg, CEO

 

The official Stock Exchange Release is given in Swedish and there may be
slight differences in the translated versions.

 

About Sotkamo Silver AB:

Sotkamo Silver AB´s business concept is to exploit mineral deposits in
the Nordic countries with regards to human society and environment.
Sotkamo Silver owns, through its subsidiary mineral deposits, which
contains silver and gold in Finland and exploration-potential targets of
zinc, lead, copper and gold in Norway. The Company’s main development
project is the Silver Mine project in the municipality of Sotkamo.

Sotkamo Silver applies SveMin’s & FinnMin’s respective rules of
reporting for public mining & exploration companies. Sotkamo Silver
has chosen to report mineral resources and mineral reserves according to
the internationally accepted JORC or NI 43-101-code. The company applies
International Financial Reporting Standards (IFRS) as approved by the
European Union.

The ticker symbol is SOSI at NGM and SOSI1 in NASDAQ OMX Helsinki.

ISIN-code for Sotkamo Silver shares are SE0001057910.

Read more about Sotkamo Silver on www.sotkamosilver.com or www.silver.fi

 

Important information

Publication or distribution of press releases in certain jurisdictions
may be restricted by law and persons in those jurisdictions where this
press release is published, or distributed should inform themselves
about and observe such restrictions.

This press release may not be released, published or distributed,
directly or indirectly, in or into Australia, Canada, Hong Kong, Japan,
New Zealand, Singapore, South Africa or the United States or any other
country where such action is wholly or partially subject to legal
restrictions. The information in this press release may not be
forwarded, reproduced, or disclosed in ways that conflict with such
restrictions. Omission to follow this instruction may result in
violation of the United States Securities Act of 1933 (\"Securities
Act\"), as amended, or applicable laws of other jurisdictions.

Statements in this press release, which are not purely historical facts,
including without limitation statements regarding future estimates,
plans, objectives, assumptions or expectations of future performance are
“forward - looking statements.

Please note that such forward - looking statements involve known and
unknown risks and uncertainties that could cause actual results and
future events to differ materially from those anticipated in such
statements. Such risks and uncertainties include fluctuations in metal
prices, unpredictable results of exploration activities, uncertainties
inherent in the estimation of mineral reserves and resources,
fluctuations in the costs of goods and services, problems associated
with exploration and mining operations, changes in legal, social or
political conditions in Finland, Sweden and Norway and lack of
appropriate funding, all of which could among other things, prevent any
of the forward looking statements in this presentation from coming to
fruition or lead to a delay in the development of mining operations.

Attachments

160322_Updated_Feasibility_Study_ENG_89a2a.pdf