Krasny license: Operational update March 2016


Kopy Goldfields AB (publ) ("Kopy Goldfields" or the "Company") hereby provides an operational update of the Krasny project:

  • The Russian GKZ reserve report was formally approved by the Russian authorities on March 30, 2016. The report awards the Krasny mineralization to be a deposit with totally 9,767 kg of gold reserves under the C2 category (314 koz).
  • An Expansion drilling program was commenced on December 14, 2015 and finalized on February 25, 2016. In total, 16 drill holes were completed, accounting for 3,504 meters of core drilling. All 36,653 fire assay tests for gold have been received.
  • A second Metallurgical processing test for the oxidized ore, based on new samples, was commenced in January 2016 and completed in March 2016, showing better recovery results than the first test.
  • The drafting of a JORC report was started in November 2015, and is currently under completion. The final report is expected during April 2016.

This operational update further develops the information provided in press release 21/2015, dated December 2, 2015, press release 22/2015, dated December 9, 2015 and press release 3/2016, dated March 2, 2016.

Drilling Exploration results
By the end of February 2016, all drilling operations for the Expansion drilling program were completed, totaling 16 drill holes and 3,504 meters of core drilling (see Figure 3 in Attachment 1 for location of the drill holes). During March 2016, all assay tests have been completed and received. Based on the assay results, we are able to delineate the extension of the upper mineralization within the Krasny deposit along the strike. Although the Upper gold mineralization continues further to the West and to the East beyond the drill profiles #35 and #59 respectively, the grade is falling below the cut-off. The strike extension of the Lower gold mineralization was not targeted with this drilling program and is left for future explorations during 2016.

The most important outcome of the expansion drilling is the new confirmation of a significant gold mineralization in the Lower structure, intersected by the holes #141755 and #141745 (both cross sections are presented on the Figure 4). Hole #141755, drilled in profile 46 demonstrated 111 meters of gold mineralization with an average grade of 2.54 gr/t. Hole #141745, drilled in profile 48 disclosed 58 meters of gold mineralization with an average grade of 1.81 gr/t. Both results do confirm the initial geological modelling for the Lower structure which was the basis for the resource estimation of the Lower structure back in 2013 and the results are also far above the average gold grade and thickness of the Upper gold mineralization.

The Lower structure was explored by Kopy Goldfields during 2011-2012, before GV Gold joined the project, and was covered by the JORC resource report for Krasny project published in early 2013. Since then, the gold price has fallen from 1,670 USD/oz used for the JORC calculations, to the current 1,230 USD/oz. For that reason, the Lower mineralization was assumed not be economical and hence not the target of the Stage 1 and 2 Exploration program developed during 2014-2015, which was instead solely devoted to the Upper mineralization. Following the completion of Stage 2 drilling in September 2015 and upon receipt of the strong mineral processing test results for the primary ore (the upper mineralization is represented by partially oxidized and partially primary rock, while the lower mineralization is represented by the primary rock only) in December 2015, production scenarios and pit optimization were modeled for both Upper and Lower structures. Modelling results now confirm that the Lower gold mineralization is potentially minable at the current market conditions. This result may radically increase the potential of the Krasny project by significantly expanding the gold reserve and including the Lower mineralization for production.

A new drilling program is discussed for 2016, targeting to explore the Lower mineralization. Development of the Upper structure into production will continue in parallel with exploration of the Lower structure.

Mineral processing results
During December 2015 - March 2016, a second mineral processing test of the oxidized rock from the Upper mineralization on Krasny has been developed using a new sample of 640 kg. The test was performed by Irgiredmet engineering consultancy in Irkutsk, which performed all the previous mineral processing tests for Krasny. The gold recovery via gravitation-flotation-leaching process totaled 78-79% (based on two experiments). This result is better than the previous results of 75% gold recovery that was released in early December 2015. The next step is to develop a detailed processing flow chart during the 2016 feasibility study activities.

Mineral resource reporting A mineral reserve report ("GKZ report") for the Krasny deposit, which was prepared in accordance with the Russian Statutory Reserve Committee ("GKZ") reporting regulations, was reviewed during the first quarter 2016 by industry experts appointed by the GKZ authorities in Irkutsk. On March 30, 2016, the report was formally approved by the Federal Agency on Subsoil Usage (subsidiary of the Russian Ministry on Natural Resources) in Krasnoyarsk. The report classifies the Krasny mineralization to be a deposit with total ore reserves under the C2 category of 6,317 ktons with an average grade of 1.55 gr/t, that makes 9,767 kg of gold (314 koz). The report recommends the deposit for pilot gold production.

The GKZ reserve report exceeds the threshold for Kopy Goldfields to qualify for the conditional consideration payment under the Shareholders agreement between Kopy Goldfields and GV Gold. The remaining required documentation is now being prepared.

In parallel to the GKZ-report, a report on mineral resources in accordance with the JORC provisions ("JORC report") is being developed. The drafting of the JORC report was started in November 2015, and is currently under completion internally. The final report is expected during April 2016.

Next steps
Following the completion of the resent exploration activities and reserve reporting, the Krasny project now moves into Pre-/Feasibility Studies. Currently, a detailed plan for 2016 and a general development plan for Krasny until production start is being finalized. For 2016, this will preliminary include further explorations for the Upper and Lower structures, development of the detailed mineral processing flow chart and FS report preparations.

We forecast the following events during the next few months: 

  • Completion of JORC report in April 2016 
  • Commence the Krasny 2016 Development Program in April-May 2016

Stockholm, April 11, 2016

For more information, please contact:
Mikhail Damrin, CEO, +7 916 808 12 17, mikhail.damrin@kopygoldfields.com
Tim Carlsson, CFO, + 46 702 31 87 01, tim.carlsson@kopygoldfields.com

The following documents can be retrieved from beQuoted
Kopy Goldfields Pressrelease 2016-04-11 English.pdf
Kopy Goldfields Pressrelease 2016-04-11 Svenska.pdf

About Kopy Goldfields AB
Kopy Goldfields AB (publ), listed at NASDAQ First North in Stockholm is a gold exploration and production company operating in one of the most gold rich areas in the world; Lena Goldfields, Bodaibo, Russia. The company holds 11 bedrock exploration- and production licenses and one alluvial license covering in total 1,963 sq km, of which the Krasny licenses (bedrock and alluvial) are held 49% by the company. The preliminary forecast is to be in production in 2018. The target for Kopy Goldfields is to become a near-term gold producer in cooperation with a producing partner under JV agreement.

Kopy Goldfields AB applies International Financial Reporting Standards (IFRS), as approved by the European Union. Aqurat Fondkommission acts as Certified Adviser, contact number: +46-8-684 05 800.

The Share
Ticker: KOPY
http://www.nasdaqomxnordic.com/shares/microsite?Instrument=SSE77457
Outstanding shares: 59,899,541


Attachments

Kopy_Goldfields_Pressrelease_2016-04-11_Svenska.pdf Kopy_Goldfields_Pressrelease_2016-04-11_English.pdf