Endomines AB Press Release, Summary Interim Report January-September 2011


Endomines delivers positive result for the Q3/2011.

Q3/2011 Highlights
  * Revenues KSEK  49,428 (-)
  * Operating  result   23,075  (-5,108) and  profits  after  tax KSEK 18,088 (-
    9,302)
  * Earnings per share  SEK 0.23 (-0.13)
  * Gold production 185.2 kg (5,957 oz)
  * A  cave-in occurred  on July  28th in the  high-grade southern ore body, the
    overall effect on production was limited
  * The  Board  of  Endomines  initiated  a  feasibility  study  with  a view to
    increasing processing capacity at Pampalo beyond 270,000 tonnes per annum
  * Exploration proceeded according to plan

Q1-Q3/2011 Highlights
  * Revenues KSEK  114,337 (-)
  * Operating  result   7,391  (-61,095) and  profits  after  tax  KSEK 6,413 (-
    71,169)
  * Earnings per share  SEK 0.08 (-0.97)
  * Gold production was 435.3 kg (13,997 oz) from February to end-September

Production guidance
  * The  Company maintains its  gold production guidance  of 550-600 kg (17,700-
    19,300 oz)  for the full year  2011 and at 800-900 kg (25,700-28,900 oz) per
    annum as from 2012.

Subsequent events
  * Trial production of gravimetric concentrate started in early October
  * In  accordance with Endomines' decision to shift to an owner-operator model,
    the  company took delivery of  a Sandvik drifting jumbo  at the Pampalo mine
    site  at the end of October. For an initial period, drifting will be carried
    out using both contractors and Endomines' own workforce and equipment.

Key financial figures

Key figures                           Q3      Q3    Q1-Q3    Q1-Q3

KSEK                               2 011   2 010    2 011    2 010

Revenues                          49 428       -  114 337        -

Operating cost                   -26 353  -5 108 -106 946  -61 095

EBIT                              23 075  -5 108    7 391  -61 095

Net finance cost                   1 256  -5 801    1 773  -12 953

Profit before tax                 24 331 -10 909    9 164  -74 048



Total cash flow for the period    12 819 -53 334   -3 735 -149 340


------------------------------------------------------------------
Cash at end of period                              54 635   65 733


Outlook

Endomines  expects production at its Pampalo  Gold Mine to progress according to
its  production  plan.  The  Company  maintains  its gold production guidance of
550-600 kg  (17,700-19,300 oz)  for  the  full  year  2011, and  at  800- 900 kg
(25,700-28,900 oz) per annum as from 2012.

The  gold price is  generally expected to  stay at high  levels, a view which is
shared  by Endomines. This will have a  positive effect on the Company financial
results  and cash flow for the proportion of sales which exceeds the hedged gold
production volume.

Cash flow from operations is expected to turn positive for the full year 2011.

CEO statement

The  Pampalo Gold Mine ramp-up was completed  during H1/2011 as per our original
schedule,  and the mine and plant  have achieved planned operational capacity of
230,000 tonnes per annum during Q3/2011.

We faced our first real operational challenge during the reporting period when a
stope in the S-lens caved in on July 28. We lost a newly delivered cable bolting
rig,  but there were no  injuries to personnel. The  rig was fully insured. This
had  a  limited  effect  on  production  tonnage  as  we  were  able to increase
production  in other areas of the mine. Longer-term, however, there will be some
increases  in costs as a consequence of the  cave-in due to the need to increase
cable-bolting. However, there will not be any need to change mining principles.

It is thanks to the dedication and hard work of our mining team that the cave-in
had  no significant effect  on gold production.   We have since  achieved a good
head grade as well as the highest level of gold output from Pampalo since coming
on-stream.

The  Pampalo processing plant continues to  show good production performance. We
are  very satisfied by the recent plant utilization rate and throughput tonnage.
However,  total Q3/2011  mining and  processing tonnage  was slightly  below our
production  target, mainly  due to  a scheduled  power line guarantee repair and
maintenance shutdown for a total of nine days in August. With debottlenecking in
the  processing plant, we have over long periods achieved hourly capacity levels
of 34 tonnes per hour. This is above the planned capacity of 32 tonnes per hour.
Further  debottlenecking will  continue with  a target  of mining and processing
270 000 tonnes of ore during 2012.

We are also pleased to have reached an agreement with Sandvik on the accelerated
delivery of a new cable-bolting rig before the year-end. It will replace the rig
which was wrecked in the July incident. Meanwhile, ground support is provided by
a contractor. In addition, a new Sandvik drifting jumbo was delivered at the end
of  October. This will speed up underground  development work and will allow for
the rapid opening of new production areas in the underground mine.

Pampalo Gold Mine
Key production indicators[1]:

                         Q1/2011 Q2/2011 Q3/2011 Q1-Q3 2011

Tonnes mined              25,382  44,050  49,441    118,873

Tonnes processed          35,797  53,169  56,915    145,881

Head grade (Au g/t)          3.5     3.1     3.7        3.5

Hourly utilization          63.4    90.5    86.7       87.7

Recovery (%)                83.8    87.0    88.1       86.4

Gold produced (kg)         105.4   144.7   185.2      435.3

Gold produced (oz)         3,390   4,651   5,957     13,997

LTIFR (12 month rolling)      39      50      42         42

Cash Cost USD/oz           1,136     919     675        833


Cash Cost[2] for the period Q3/2011 was 675 USD/payable ounce of gold. Cash Cost
for  Q1-Q3 was  833 USD per  payable ounce.  Endomines expects  future Cash Cost
levels  for the Pampalo Gold Mine to  be lower after the ramp-up phase, although
it  will remain higher than the 520 USD indicated earlier and which was based on
the Pampalo Gold Mine feasibility studies. This increase reflects the lower gold
production  levels  published  in  Endomines'  Q2  report  as  well as generally
increased production costs and drifting volumes in the mine.

Drifting  and other operating costs of  mining operations can vary significantly
from  quarter to quarter,  thus affecting the  Cash Cost. Furthermore, cash cost
calculations  depend on a number of variables  which can be difficult to predict
accurately  and can thus change significantly over time. Endomines has therefore
taken  the decision to no longer issue  future cash cost estimates but will only
publish actual cash cost levels per quarter and per annum.

Environmental  consulting  company  Linnunmaa  Oy  was  contracted to conduct an
Environmental Permit Renewal process, including a further capacity increase to a
level  above  270 000 tonnes  per  annum.  The  application  is  expected  to be
completed  in January 2012, and the final decision can be expected before autumn
next year.

There  was one Lost Time Injury during the quarter, resulting in one day of sick
leave.  The number  of personnel  at the  Pampalo Gold  Mine at  the end  of the
reporting  period was 55 own, 25 contractor employees and 10 short-term seasonal
substitutes.

With  regards to  personnel, one  of Endomines'  main challenges,  and one which
affects  the whole mining  industry in  in the  Nordic region,  is a shortage of
qualified  personnel for  key positions.  In order  to help  resolve this issue,
Endomines   has   taken  the  decision,  amongst  other  measures,  to  actively
participate in various mining industry initiatives and education programs.

[1]  Production figures  for Q1-Q2  are final  and based  on the  assay exchange
procedure between Boliden Harjavalta Oy and Endomines Oy, Production figures for
Q3 are mainly based on assays carried out by the Pampalo Gold Mine laboratory.
[2]  Endomines calculates"Cash cost" per ounce figures using the guidance issued
by  The Gold Institute Production Cost  Standard.  Direct mining, ore processing
and  site administration, and off-site smelting  and refining costs are included
in  the "Cash  cost" calculation,  but amortization,  stock change, reclamation,
capital  and  exploration  costs  are  excluded.  "Cash  cost" is calculated per
payable  ounces. "Cash cost"  figure is given  to provide additional information
and  is a  non-IFRS measure.   Conversion from  EUR to  USD is made by using the
average  exchange rate for the period, ie 1.37 for Q1/2011, 1.44 for Q2/2011 and
1.41 for Q3/2011. For January-September the rate was 1.40.

Exploration

Airborne  low-altitude  geophysical  surveys  were  completed in July, and final
results of these were received in August. Several new drilling targets have been
discovered all over the claimed areas.

During  the period, exploration drilling has been carried out in the vicinity of
Pampalo,  as well as  in the Hosko,  Rämepuro and Korvilansuo  areas. A total of
some  5,400 meters of  the planned  7,000 meter campaign  for the year 2011 have
been  drilled.  Our drilling contract included an  option to increase this by an
additional 2,000 meters of drilling.  Endomines has recently decided to exercise
the option, and has notified the contractor accordingly.

Several assays are still pending due to the high work load at all laboratories.

Final  results of  the summer  exploration campaign  will be  published once all
relevant information has been compiled.

The  mining authorities granted 50 additional  reservation areas (~35,000 ha) to
Endomines during the period, all located on the Karelian Gold Line.
An Environmental Impact Assessment (EIA) program hearing was held in Hattuvaara,
with  public opinions  and official  statements expected  by the end of November
2011. The  final regional EIA -report is scheduled to be ready for review by the
authorities in January 2012.

The  number of exploration personnel  at the end of  the reporting period was 3
own,  8 contractor  employees  in  drilling,  as  well  as 3 short-term seasonal
substitutes.

Industrial Minerals

Endomines  continued  to  work  on  strategic  alternatives  with regards to its
Industrial Minerals assets.

Gold price hedge

In December 2009, Endomines hedged 84,400 oz of its future gold deliveries up to
and  including the year 2015. The hedge price was 843 EUR per oz.  The period H1
2011 was  unhedged. Endomines applies hedge accounting,  and thus any changes in
market   value   of    yet  unexecuted  deliveries  are  included  under  "Other
Comprehensive  Income" and therefore  do not affect  "Net Profits After Tax". An
exception  to this is when  the hedge is  not 100% effective. In  this case, the
ineffective part of the hedge is included under "Operating Costs".

The  market value  of the  hedge is  driven by  several factors such as the gold
price  in USD as  well as changes  in the EUR/USD  exchange rates. A higher gold
price leads to a weakening of the market value of the hedge derivatives.

As  from Q3 2011, the revenues from the hedged production volume will be reduced
by the difference between the average price per quarter and the hedge price. The
hedged  production volume in  Q3 was 4,500 oz.   Sales over this  volume were at
market price.

General Corporate

Work continued according to plan with a view to preparing Endomines' application
to list on the main market of NASDAQ OMX Nordic Stockholm. The application is
expected to be submitted during Q4/2011.

Endomines  Board of Directors took the  decision to publish estimated production
figures  for  2012 in  its  full-year  report  scheduled  for February 2012. Ore
reserve  calculations will be updated at  year-end and published once these have
been finalized.

A full interim report (in Swedish) is available on the Company's website.

For further information, please contact:
Markus Ekberg, CEO of Endomines AB
tel. +358 40 706 48 50
Or visit the Company's website atwww.endomines.com

About Endomines AB

Endomines AB is a Nordic mining and exploration company with its first operating
gold  mine in  production since  February 2011. The  mine is  located in Eastern
Finland,  on the  Karelian Gold  Line, a  40 km long  gold critical  belt, where
Endomines controls all currently known gold deposits.

The  company has several other gold and industrial mineral properties at various
stages  of development.  All Endomines'  mineral assets  are located in Finland,
which is politically stable, has a highly developed infrastructure and is ranked
as one of the most favorable jurisdictions for the mining industry.

Endomines  aims to increase shareholder value by developing its strong portfolio
of  assets, as well as  exploring new deposits on  the Karelian Gold Line and in
Finnish   Lapland.   The  company  will  also  consider  new  opportunities  and
acquisitions for further growth.

The  company's business practices and mining operations are based on sustainable
principles and on minimizing the impact on the environment.

Endomines  applies SveMin's &  FinnMin's respective rules  for reporting (public
mining  & exploration companies). It has also chosen to report mineral resources
and  ore  reserves  according  to  the  JORC-code,  which is the internationally
accepted  Australasian code  for reporting  ore reserves  and mineral resources.
Endomines applies International Financial Reporting Standards (IFRS) as approved
by the European Union.
Endomines  AB shares are quoted on the  First North Premier segment in Stockholm
under  ticker ENDO.ST. Erik Penser Bankaktiebolag  acts as Certified Adviser and
Liquidity Provider.

Read more about Endomines on www.endomines.com
---
This  news  release  may  contain  forward-looking statements, addressing future
events  and conditions which are subject to various risks and uncertainties. The
Company's   actual   results,  programs  and  financial  position  could  differ
materially from those anticipated in such forward-looking statements as a result
of  numerous factors, some of  which may be beyond  the Company's control. These
factors  include  the  availability  of  funds,  the  timing and content of work
programs,   results   of  exploration  activities  and  development  of  mineral
properties,  the interpretation of  drilling results and  other geological data,
the  uncertainties of resource and reserve  estimations, receipt and security of
mineral  property  titles,  project  cost  overruns  or  unanticipated costs and
expenses, fluctuations in metal prices, currency fluctuations and general market
and industry conditions.
Forward-looking  statements are  based on  the expectations  and opinions of the
Company's  management on the date the  statements are made. The assumptions used
in  the preparation  of such  statements, although  considered reasonable at the
time  of preparation,  may prove  to be  imprecise and,  as such, undue reliance
should not be placed on forward-looking statements.

[HUG#1563368]

Anhänge