Excerpt from pages 330 and 331 of Talon Metals Corp.'s Preliminary Economic Assessment #3 on the Tamarack North Project (NI 43-101 technical report, January 8, 2021), showing the Nickel Concentrate Scenario and Table 22-15, "C1 Cost of the Ni Concentrate Scenario". The highlighted row, added by First Atlantic, shows smelting, refining and deductions by the smelter of US$692.0 million over the life of mine, or US$2.66 per pound of nickel in concentrate, compared with on-site cash costs of US$1.91 per pound.