Civil Engineering Contracts Awarded for Nalunaq Gold Mine


VANCOUVER, Canada, July 2, 2003 (PRIMEZONE) -- Crew Development Corporation ("Crew") (TSE:CRU) (OSE:CRU) (Frankfurt:KNC) (Other OTC:CRWVF): Crew is pleased to announce that the Board of Nalunaq Gold Mine (NGM) has approved the key civil engineering contracts for the Nalunaq Gold Project. This will initiate the construction of the required infrastructure for both mining and shipping of the ore at the company's high-grade gold deposit in South Greenland.

The largest single contract, which is the delivery of a turnkey camp complex for 70 people, was awarded to a south Greenlandic contractor in cooperation with a Norwegian camp supplier. The contractor, RC Enterprise Service ApS of Qaqortoq in South Greenland ("RC"), was selected in a competitive bidding for the camp complex from 10 vendors, including 5 North American and 5 Scandinavian/Greenlandic contractors. The contact covers all mobilization, construction and earthworks, including water supply and wastewater treatment, as well as installation of 400 MW power facilities. RC has also been engaged to upgrade and extend the access roads and prepare a new stockpile pad at the shipping site.

On the marine side, Dykkerselskabet Viking A/S ("Viking") of Nuuk, Greenland, was awarded the contract to construct and prepare the anchor systems for the barge and bulk carrier and to mobilize and install the 300-foot barge to be used as support for the ship loader facility. Viking, in cooperation with a Danish supplier, was selected from 4 international quotations, to also supply and construct the conveyor system and the ship loader.

The remaining contracts to be finalized include the shipping and mining contracts, as well as the processing agreement, to be completed in August and September 2003. Nalunaq Gold Mine AS and Crew are currently working with a modification of the mine plan to increase the productivity and reduce cost, and thereby further improving the economics of the mine.

The construction work has started and the camp and harbour facilities are expected to be fully operational in September 2003. Mining operations are scheduled to commence immediately thereafter, subject to a final technical approval by the authorities.



                    Jan A. Vestrum
                    President & CEO

This news release contains certain "Forward-Looking Statements". All statements, other than statements of historical fact, included in this release, and/or statements made by company officers or directors at any given time, as well as Crew's future plans are such forward-looking statements that involve various risks and uncertainties. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements are based on the estimates and opinions of management on the date the statements are made, and Crew does not undertake any obligation to update forward-looking statements should conditions or management's estimates or opinions change.