Photo 1 and 2
Bunker Hill Provides November 2022 Project Restart Update
December 01, 2022 17:39 ET | Bunker Hill Mining Corp.
HIGHLIGHTS Abatement of maintenance shop complete, demolition to prepare for new mill building underwayCommitment made to new Bunker Hill pre-engineered mill building design and vendor Underground...
Bunker Hill.png
Bunker Hill Announces Marketed Public Offering
November 22, 2022 08:00 ET | Bunker Hill Mining Corp.
TORONTO, Nov. 22, 2022 (GLOBE NEWSWIRE) -- Bunker Hill Mining Corp. (the “Company”) (CSE: BNKR) is pleased to announce that it has filed a preliminary short form prospectus (the “Prospectus”) with...
Bunker Hill.png
Bunker Hill Announces New $5,000,000 Loan Facility From Sprott and Provides Update on Project Finance Process
November 18, 2022 07:00 ET | Bunker Hill Mining Corp.
TORONTO, Nov. 18, 2022 (GLOBE NEWSWIRE) -- Bunker Hill Mining Corp. (the “Company”) (CSE: BNKR, OTCQB: BHLL) is pleased to announce a new loan facility from Sprott Private Resource Streaming &...
Photo 1
Bunker Hill Provides October 2022 Project Restart Update
November 03, 2022 07:00 ET | Bunker Hill Mining Corp.
HIGHLIGHTS Demolition activities at Pend Oreille site completed ahead of schedule and under budgetProcurement of new Bunker Hill mill building initiated, concurrent with abatement and demolition of...
Bunker Hill.png
Bunker Hill Mining Announces Filing of PFS Technical Report
October 18, 2022 21:41 ET | Bunker Hill Mining Corp.
TORONTO, Oct. 18, 2022 (GLOBE NEWSWIRE) -- Bunker Hill Mining Corp. (the “Company”) (CSE: BNKR) is pleased to announce filing of an independent Preliminary Feasibility Study (“PFS”) for the Bunker...
Photo 1:
CORRECTION -- Bunker Hill Provides September 2022 Project Restart Update
October 05, 2022 11:07 ET | Bunker Hill Mining Corp.
Live 6ix Summit Today, Wednesday October 5 @ 11:00am ET / 8:00am PT HIGHLIGHTS Phase 1 Prefeasibility Study results reported, envisaging low capex, high-margin restart with average annual FCF of...
Photo 1:
Bunker Hill Provides September 2022 Project Restart Update
October 05, 2022 07:00 ET | Bunker Hill Mining Corp.
Live 6ix Summit Today, Wednesday October 5 @ 11:00am ET / 8:00am PT HIGHLIGHTS Phase 1 Prefeasibility Study results reported, envisaging low capex, high-margin restart with average annual FCF of...
Bunker Hill.png
Bunker Hill Secures Ball Mill Capable of Increasing Annual Production Throughput Capacity to 2,100 tpd
September 20, 2022 07:00 ET | Bunker Hill Mining Corp.
HIGHLIGHTS: Enables production throughput of 1,800 tons per day (tpd) as envisaged in the Prefeasibility StudyPotential capacity of up to 2,100 tpd, subject to future detailed engineering and mine...
Bunker Hill.png
Bunker Hill Announces Prefeasibility Study for First Phase of Mine Restart
September 06, 2022 07:00 ET | Bunker Hill Mining Corp.
Bunker Hill to Host Live Interactive 6ix Summit on Thursday, September 8 @ 2:00pm ET / 11:00am PT HIGHLIGHTS: Average annual FCF of >$25 million, EBITDA of >$40 million, and zinc-equivalent...
Photo 1
Bunker Hill Provides August 2022 Project Restart Update
August 31, 2022 18:30 ET | Bunker Hill Mining Corp.
HIGHLIGHTS Demobilization of Pend Oreille Mill completed safely, ahead of schedule and on budgetUnderground decline advances, plan optimized to improve ventilation on break-through to 6...