THIS ANNOUNCEMENT IS NOT FOR RELEASE, PUBLICATION OR DISTRIBUTION IN OR INTO THE UNITED STATES Xcite Energy Limited (
-- High porosity and permeability unconsolidated sandstone
-- Temperature of over 103 degrees Fahrenheit
-- Depth to top of reservoir 3712ft
-- No gas cap
Based on these well test results, the Company believes that commercially
viable production rates are achievable through the application of
horizontal well technology coupled with appropriate artificial lift,
including submersible pumps. The Company now intends to proceed with
planning for the next phase of the development process for the Bentley
field, which will utilise EOR techniques consistent with the qualities of
the reservoir and characteristics of the crude oil.
Based on the success of the 9/3b-5 appraisal well, the Company now intends
to re-process the 3D seismic data over the Block to confirm the results of
its recent 3D interpretation, which indicated a material increase in STOIIP
compared to the 2D seismic.
In addition, the Company will move forward to plan further and identify the
optimum methodology for the future commercial development of the Bentley
field. As part of this work programme, the Company intends to update the
work performed by RPS Energy Canada Ltd to provide a revised Competent
Person's Report.
The Bentley heavy oil field is located on Block 9/3b (licence P. 1078), in
which Xcite Energy holds 100% working interest. Block 9/3b is approximately
160km east of the Shetland Isles with an area in excess of 200 km². Bentley
has been drilled by three of the four previous wells on Block 9/3b, being
wells 9/3-1 (Amoco, 1977), 9/3-2A (Conoco, 1983) and 9/3-4 (Conoco, 1986).
This is the fifth well on the Block.
Richard Smith, Chief Executive Officer of Xcite Energy, commented:
"The outstanding success of the 9/3b-5 appraisal well takes us past another
of our key milestones for the Xcite Energy business and for the Bentley
field, one of the largest undeveloped heavy oil fields in the North Sea. We
are grateful to all those who have helped achieve this success and we now
turn our attention to the next phase of commercialising the Bentley field
within the Company's expected timescale."
Stephen Kew has reviewed and approved the technical information contained
within this press release in his capacity as a competent person, as
required under the AIM rules. Stephen Kew is Head of Exploration and
Development at Xcite Energy and is an associate of the Institution of
Chemical Engineers and a member of the Society of Petroleum Engineers.
The TSX Venture Exchange does not accept responsibility for the adequacy or
accuracy of this release.
Glossary
"bbls/d" means barrels per day.
"best estimate" is considered to be the best estimate of the quantity that
will actually be recovered from an accumulation and, if probabilistic
methods are used, this term is a measure of central tendency of the
uncertainty distribution (most likely/mode, P50/median, or arithmetic
average/mean).
"crude oil" means a mixture that consists mainly of pentanes and heavier
hydrocarbons, which may contain sulphur and other non-hydrocarbon
compounds, that is recoverable at a well from an underground reservoir and
that is liquid at the conditions that is recoverable at a well from an
underground reservoir and that is liquid at the conditions under which its
volume is measured or estimated. It does not include solution gas or
natural gas liquids.
"discovered resources" means those quantities of oil and gas estimated on a
given date to be remaining in, plus those quantities already produced from,
known accumulations. Discovered resources are divided into economic and
uneconomic categories, with the estimated future recoverable portion
classified as reserves and contingent resources, respectively.
"drill stem test" means a procedure for testing the surrounding geological
formation using specialised tubing.
"EOR" means enhanced oil recovery.
"field" means an area consisting of a single reservoir or multiple
reservoirs all grouped on or related to the same individual geological
structural feature and/or stratigraphic condition.
"heavy oil" means oil with API gravity of less than 22 degrees and
reservoir viscosity greater than 5 centipoise.
"mmbbls" means million barrels.
"reservoir" means a porous and permeable underground formation containing a
natural accumulation of producible oil or gas that is confined by
impermeable rock or water barriers and is individual and separate from
other reservoirs.
"STOIIP" means stock tank volume of oil initially-in-place.
Forward-Looking Statements
Certain statements contained in this announcement constitute
forward-looking information within the meaning of securities laws.
Forward-looking information may relate to the Company's future outlook and
anticipated events or results and, in some cases, can be identified by
terminology such as "may", "will", "should", "expect", "plan",
"anticipate", "believe", "intend", "estimate", "predict", "target",
"potential", "continue" or other similar expressions concerning matters
that are not historical facts. These statements are based on certain
factors and assumptions including expected growth, results of operations,
performance and business prospects and opportunities. While the Company
considers these assumptions to be reasonable based on information currently
available to us, they may prove to be incorrect. Forward-looking
information is also subject to certain factors, including risks and
uncertainties that could cause actual results to differ materially from
what we currently expect. These factors include changes in market and
competition, governmental or regulatory developments and general economic
conditions. Additional information identifying risks and uncertainties are
contained in Xcite Energy' prospectus filed with the Canadian securities
regulatory authorities, available at www.sedar.com.
Contact Information: Enquiries: Xcite Energy +44 (0) 1330 826 740 Richard Smith Chief Executive Officer Rupert Cole Chief Financial Officer Thomas Weisel Partners (UK) Limited +44 (0) 20 7290 9716 Paul Colucci Managing Director Paul Newman Managing Director Strand Partners Ltd. +44 (0) 20 7409 3494 James Harris Director Warren Pearce Associate Director Pelham Public Relations +44 (0) 20 7743 6676 Alisdair Haythornthwaite Director Katherine Stewart Account Executive Lucy Frankland Account Executive