IT – Nasdaq Nordic Primary Data Center Relocation Project Update – INET – REMINDER: Launch Weekend Schedule


This IT Notice contains launch time schedule for INET (Cash Equity).

As previously communicated, Nasdaq is in the process of relocating its primary data center from the current LUNDA data center to the new VASBY data center. This relocation affects all customers, service- and connectivity providers with connectivity to LUNDA data center.

Customers that have not adapted to new IP´s and ports by June 20th will not be able to access the new INET environment in VASBY.
 

INET (Cash Equity) Production launch time schedule

Saturday June 18th, 14:00 – 17:00 (CEST) – Final login verification test

  • New INET in VASBY promoted as the Primary Production site
  • INET PORT will remain as the Secondary/Failover Production site
  • INET LUNDA is discontinued (no logins or ITCH MC services)
  • No markets open (only heartbeats to verify ITCH MC connections)
  • Customer login verification test will be arranged between 14:00 – 17:00 CEST

Please confirm via e-mail to technicalrelations@nasdaq.com, as soon as you have completed your INET migration from LUNDA to the VASBY data center (latest by June 18 at 17:00 CEST)
 

Monday June 20th à INET Data Center Relocation completed

  • New INET in VASBY promoted as the Primary Production site
  • INET PORT will remain as the Secondary/Failover Production site
  • INET LUNDA is discontinued (no logins or ITCH MC services)
     



Additional information:

  • Please see attached “Weekend Migration Plan” for important information regarding the launch weekend activities, including communication plan and rollback plan
  • General INET VASBY connectivity information is available at the Data Center Relocation website
  • Members individual port information has been distributed to all clients. If you haven’t received the new connectivity details please contact operator@nasdaq.com
  • Members accessing INET ports from new source IP’s/subnets need to inform operator@nasdaq.com the new details (source IP validation)
  • Good-Till-Cancelled (GTC) orders will remain in INET during the migration; no action is required by customers

Data Center Relocation website:

http://www.nasdaqomx.com/transactions/technicalinformation/data-center-relocation

 

Contact

INET - Technical issues, Account/Port configurations:
operator@nasdaq.com
+46 8 405 6410


Questions regarding this IT-Notice:

ronny.thellman@nasdaq.com
+46 8 405 6313 

or:

technicalrelations@nasdaq.com

 