Victoria Gold: Eagle Gold Mine Q3 2023 Production


WHITEHORSE, Yukon, Oct. 04, 2023 (GLOBE NEWSWIRE) -- Victoria Gold Corp. (TSX-VGCX) (“Victoria” or the “Company”) produced 41,561 ounces of gold during the period July 1 to September 30, 2023, the third quarter (“Q3”) of 2023. Year-to-date 2023 gold production is 124,749 ounces.

Eagle Gold Mine Q3 2023 Production Results

  3rd Quarter 20233rd Quarter 20229 Months 20239 Months 2022
Operating Data     
Ore minedmillions of tonnes2.12.16.65.6
Waste minedmillions of tonnes2.83.08.07.5
Total minedmillions of tonnes4.95.114.613.1
Strip ratiowaste to ore1.31.51.21.3
Mining rate000’s of tonnes/day53565348
Ore stacked on padmillions of tonnes2.32.16.95.3
Ore stacked gradegrams/tonne Au0.650.890.750.84
Gold producedounces41,56150,028124,749106,441

Q3 2023 statistics may be subject to immaterial reconciliation variances.

Gold production was up by 17% in the first 9-months of 2023 compared to the same period in 2022 while Q3 production decreased 17% year-over-year. Both the quarterly decrease year-over-year and the 9-month year-to-date increase are due to a reduction in seasonality as a result of year-round ore stacking on the heap leach pad, a more even distribution of planned maintenance throughout the year and a growing heap leach pad which moderates quarter over quarter gold production. The quarter-over-quarter decrease in grade is due to mine sequencing. Ore and waste mined, ore stacked on the heap leach pad and gold produced were all negatively impacted during the 3rd quarter of 2023 by an approximate 2 week evacuation in early August due to wildfire activity.

Qualified Person
The technical content of this news release has been reviewed and approved by Paul D. Gray, P.Geo., as the “Qualified Person” within the meaning of National Instrument 43-101 - Standards of Disclosure for Mineral Projects.

About the Dublin Gulch Property
Victoria Gold's 100%-owned Dublin Gulch gold property (the “Property”) is situated in central Yukon Territory, Canada, approximately 375 kilometers north of the capital city of Whitehorse, and approximately 85 kilometers from the town of Mayo. The Property is accessible by road year round, and is located within Yukon Energy's electrical grid.

The Property covers an area of approximately 555 square kilometers and is the site of the Company's Eagle and Olive Gold Deposits. The Company issued a National Instrument 43-101 Technical Report for the Eagle Gold Mine dated April 10, 2023 (the “2023 Eagle Technical Report”). As at December 31, 2022, the Eagle and Olive deposits include Proven and Probable Reserves of 2.6 million ounces of gold from 124 million tonnes of ore with a grade of 0.65 grams of gold per tonne. As at December 31, 2022, the Mineral Resource for the Eagle and Olive deposits set forth in the 2023 Eagle Technical Report has been estimated to host 245 million tonnes averaging 0.59 grams of gold per tonne, containing 4.7 million ounces of gold in the Measured and Indicated category, inclusive of Proven and Probable Reserves, and a further 35 million tonnes averaging 0.62 grams of gold per tonne, containing 0.7 million ounces of gold in the Inferred category.

Cautionary Language and Forward-Looking Statements
This press release includes certain statements that may be deemed "forward-looking statements". Except for statements of historical fact relating to Victoria, information contained herein constitutes forward-looking information, including any information related to Victoria's strategy, plans or future financial or operating performance. Forward-looking information is characterized by words such as “plan”, “expect”, “budget”, “target”, “project”, “intend”, “believe”, “anticipate”, “estimate” and other similar words, or statements that certain events or conditions “may”, “will”, “could” or “should” occur, and includes any guidance and forecasts set out herein (including, but not limited to, production and operational guidance of the Corporation). In order to give such forward-looking information, the Corporation has made certain assumptions about its business, operations, the economy and the mineral exploration industry in general. In this respect, the Corporation has assumed that production levels will remain consistent with management’s expectations, contracted parties provide goods and services on agreed timeframes, equipment works as anticipated, required regulatory approvals are received, no unusual geological or technical problems occur, no material adverse change in the price of gold occurs and no significant events occur outside of the Corporation's normal course of business. Forward-looking information is based on the opinions, assumptions and estimates of management considered reasonable at the date the statements are made, and are inherently subject to a variety of risks and uncertainties and other known and unknown factors that could cause actual events or results to differ materially from those described in, or implied by, the forward-looking information. These factors include the impact of general business and economic conditions, global liquidity and credit availability on the timing of cash flows and the values of assets and liabilities based on projected future conditions, anticipated metal production, fluctuating metal prices, currency exchange rates, estimated ore grades, possible variations in ore grade or recovery rates, changes in accounting policies, changes in Victoria's corporate resources, changes in project parameters as plans continue to be refined, changes in development and production time frames, the possibility of cost overruns or unanticipated costs and expenses, uncertainty of mineral reserve and mineral resource estimates, higher prices for fuel, steel, power, labour and other consumables contributing to higher costs and general risks of the mining industry, failure of plant, equipment or processes to operate as anticipated, final pricing for metal sales, unanticipated results of future studies, seasonality and unanticipated weather changes, costs and timing of the development of new deposits, success of exploration activities, requirements for additional capital, permitting time lines, government regulation of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims, limitations on insurance coverage and timing and possible outcomes of pending litigation and labour disputes, risks related to remote operations and the availability of adequate infrastructure, fluctuations in price and availability of energy and other inputs necessary for mining operations. Although Victoria has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in, or implied by, the forward-looking information, there may be other factors that cause actions, events or results not to be anticipated, estimated or intended. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The reader is cautioned not to place undue reliance on forward-looking information. The forward-looking information contained herein is presented for the purpose of assisting investors in understanding Victoria's expected financial and operational performance and Victoria's plans and objectives and may not be appropriate for other purposes. All forward-looking information contained herein is given as of the date hereof, as the case may be, and is based upon the opinions and estimates of management and information available to management of the Corporation as at the date hereof. The Corporation undertakes no obligation to update or revise the forward-looking information contained herein and the documents incorporated by reference herein, whether as a result of new information, future events or otherwise, except as required by applicable laws.

For Further Information Contact:
John McConnell
President & CEO
Victoria Gold Corp
Tel: 604-696-6605
ceo@vgcx.com